| Project Work Plan (draft) |
April 2011 |
| Public Involvement Plan (draft) |
April 2011 |
| Project Work Plan (final) |
May 2011 |
| Community Outreach Plan (final) |
May 2011 |
| Project Website On-line |
May 2011 |
| Stakeholders List Developed |
May 2011 |
| Brownfields Task Force Established |
March-May 2011 |
| Launch On-Line Survey |
May 2011 |
| Fact Sheet #1 – Introduce Project/Survey |
May 2011 |
| Public Meeting #1 – Introduce Project/ Survey |
May 2011 |
| Brownfields Brochure Available |
June 2011 |
| Fact Sheet #2 – Inventory Results/Ranking |
August 2011 |
| Public Meeting #2 – Inventory Results/Ranking |
August 2011 |
| Phase I Environmental Site Assessment Reports (12) |
September 2011-October 2012 |
| Project-Wide Quality Assurance Project Plan |
April 2012 |
| Fact Sheet #3 – Phase 1 Update/Phase II Selection |
June 2012 |
| Public Meeting #3 – Phase 1 Update/Phase II Selection |
June 2012 |
| Complete Sampling & Analysis Plans/Health & Safety Plans (4) |
February 2012-February 2013 |
| Phase II Reports (4) |
September 2012-May 2013 |
| Fact Sheet #4 – Phase II Update/Project Wrap-up |
August 2013 |
| Public Meeting #4 – Phase II Update/Project Wrap-up |
August 2013 |
| Cleanup Plans (2) |
May-August 2013 |